This article covers the process from July 31, 2026, when the interior work began, until the opening on September 5th.


August 21
The display stand has arrived.



August 19
Detailed work by the staff.



August 16
Precise adjustment of the lighting rail using a spirit level.


August 11
The white walls are now complete.



August 9
The white wall construction is progressing.


August 7
Day 1 of creating the white wall.



August 6
The priming process for the paint has begun.
The automatic doors have been adjusted and preparations for the opening are underway.



August 5th
Construction of the walls and ceilings is progressing steadily.
Preparations for the opening are progressing smoothly.
410Gallery Plus was featured in an interview by "Monthly Hakata" magazine.
It will be published in the September 1st issue. Please be sure to check it out.



August 3
The movable wall is nearing completion.
The wall is being filled with putty. Apparently, the puttying process involves filling and sanding three times.



August 1st
Construction of the wall has begun.
Construction is progressing thanks to the meticulous work of the craftsmen.



July 31
Blue tarpaulin on the floor
I removed the old wallpaper from the interior.